Human Performance Centre, GSK Ware

Sectors: Pharmaceutical and Manufacturing

Client: GlaxoSmithKline

Construction Value: £2 million

Involvement: RIBA stages 0-7


PROJECT:

Project involved the remodelling of ground floor areas to form a new movement lab and briefing room. The first floor was remodelled to form new sensory labs, product branding lab and support areas.

FACILITIES AREA:

  • Ground Floor: New Movement Lab

  • First Floor: New Sensory Labs and Product Branding Lab

PROGRAMME:

Concept Design Commenced: February 2016

Start on Site: Sept 2016

Handover: June 2017

SCOPE OF SERVICES:

Simons Design provided architectural design services to develop Concept, Scheme and Detail Design proposals and provided technical support throughout the pre-construction and construction phases, to handover.