Oral Solid Dose Micronising Facility, GSK Ware
Sectors: Pharmaceutical and Manufacturing
Client: GlaxoSmithKline
Construction Value: £4.1 million
Involvement: RIBA stages 0-7
PROJECT:
New OSD Micronising Manufacturing Facility
FACILITIES AREA:
Ground Floor: 260sqm
First Floor: 135sqm
The project involved the design of a new OSD Manufacturing Facility providing Grade D quality space, careful integration of the Equipment requirements was required to coordinate the equipment and facility requirements to ensure the production operations were fully considered within the facility design.
PROGRAMME:
Detail Design: Completed Sept 2014
Start on Site: January 2015
Handover: December 2015
SCOPE OF SERVICES:
Simons Design provided a multi-disciplinary design team to develop Concept, Scheme and Detail Design proposals and provided technical support throughout the pre-construction and construction phases, to handover.
The design proposals were developed in BIM to enable detailed coordination of the equipment and services.